Deprecated: PragmaRX\Recovery\Recovery::__construct(): Implicitly marking parameter $random as nullable is deprecated, the explicit nullable type must be used instead in /home/customer/www/pearsonindustries.com.au/public_html/wp-content/plugins/sg-security/vendor/pragmarx/recovery/src/Recovery.php on line 28

Under Section 57 of the Heritage Act 1977 (NSW), no person may knowingly carry out works to a property listed on the NSW State Heritage Register without either a specific exemption or the written approval of the Heritage Council of NSW. For properties listed only in a council’s Local Environmental Plan (LEP), Section 4.66 of the Environmental Planning and Assessment Act 1979 requires a Heritage Impact Statement (HIS) to accompany any development application. A second storey addition to a heritage-listed property — whether State or locally listed — is not automatically prohibited, but it is subject to a higher standard of scrutiny than works to non-heritage properties. The Heritage Council of NSW’s guidelines for additions to heritage buildings draw on the Australia ICOMOS Burra Charter principle of ensuring that new work is distinguishable from the original while remaining compatible in scale, materials, and character. In practice, this means a second storey addition to a heritage home in NSW can be approved, but only if it is designed to be subservient to and compatible with the heritage significance of the original structure. This article explains exactly what that means in practice, what the approval process involves, and the typical costs.

State Listed vs Locally Listed: Two Different Regimes

The first step when considering any work to a heritage-listed home is understanding which heritage list your property appears on — because the approval regime, timeframe, and level of scrutiny differ significantly:

State Heritage Register (SHR)Local Heritage Item (LEP)
Listed byHeritage Council of NSW (under Heritage Act 1977)Local council (in their Local Environmental Plan)
Approving body for worksHeritage Council of NSW (or their delegate)Local council (via Development Application)
Approval mechanismSection 57 approval or listed exemptionDevelopment Application with Heritage Impact Statement
Typical approval timeframe3–9 months (Heritage Council review + council DA)4–9 months (council DA process)
Who to engageHeritage architect + heritage consultant for SHR Statement of SignificanceHeritage architect + heritage consultant for HIS
Can a CDC be used?No — heritage items are excluded from CDC pathwayNo — heritage items are excluded from CDC pathway

To confirm which list your property is on: search the NSW State Heritage Register at heritage.dpie.nsw.gov.au, and check your council’s Local Environmental Plan via the NSW Planning Portal at pp.planningportal.nsw.gov.au. Properties can appear on both lists simultaneously.

Can a Second Storey Be Approved on a Heritage Home?

Yes — second storey additions to heritage homes are routinely approved in NSW, including in Sydney’s most heritage-dense councils (Mosman, North Sydney, Inner West, City of Sydney, Willoughby). However, approval depends on the design meeting the Heritage Council’s guidelines for additions to heritage places. The key design principles that determine approvability are:

  • Subservience: The new addition should not dominate the original heritage structure. A second storey that exceeds the bulk and scale of the original ground floor is unlikely to be approved. The addition should “read” as clearly secondary to the original building.
  • Setback from original facade: The addition should be set back from the original front facade of the house, typically by a minimum of 1,500–2,000mm (or more for prominent heritage streetscapes). This prevents the addition from being visible from the street and preserving the heritage streetscape.
  • Compatible materials: Materials should be complementary to but distinguishable from original heritage fabric. Using identical materials and detailing to replicate the original style is sometimes called “false historicism” and is discouraged by the Burra Charter — the addition should be contemporary in character while sympathetic in scale and materiality.
  • Reversibility: The addition should be designed so it could theoretically be removed in the future without damaging the original heritage fabric.
  • Preservation of character-defining elements: Rooflines, chimneys, original windows, decorative plasterwork, and other features that contribute to heritage significance should be retained and protected.

The Approval Process: Step by Step

Step 1: Pre-Application Meeting with Council (4–6 weeks)

Before preparing a formal DA, a pre-application meeting with the council’s heritage planning officer is strongly recommended. This meeting allows you to present a preliminary concept design and get early feedback on whether the proposal is likely to be supported. Many councils require pre-application meetings for heritage DAs. Cost: $500–$2,000 in council fees, plus architect and heritage consultant time.

Step 2: Engage a Heritage Architect and Prepare Design (8–16 weeks)

A heritage architect (a registered architect with specific heritage experience and typically listed on the AICOMOS or NSW Heritage Office practitioner directory) will prepare concept and detailed design drawings that satisfy both the heritage requirements and NCC structural/energy efficiency standards. The design must clearly demonstrate setback from the original facade, compatible materials, and the distinction between new and original fabric. Heritage architect fees for a residential second storey addition typically range from $12,000–$30,000 depending on complexity.

Step 3: Prepare Heritage Impact Statement (4–8 weeks)

A Heritage Impact Statement (HIS) must accompany the DA. The HIS is prepared by a heritage consultant and must identify the heritage significance of the property (drawing from the Statement of Significance), describe the proposed works, assess the impact on heritage significance, and justify why the impacts are acceptable under the Burra Charter principles. For a second storey addition, the HIS is a substantial document and typically costs $5,000–$15,000.

Step 4: Lodge Development Application and Council Assessment (3–9 months)

The DA is lodged with the council and referred to the council’s heritage advisor (and, for SHR items, to the Heritage Council of NSW) for assessment. Neighbour notification period is typically 14–21 days. The council may request modifications to the design before granting consent. Consent conditions often specify materials, colours, and the requirement for a heritage specialist to inspect works at key stages.

Typical Total Costs for a Heritage Second Storey Addition

Cost ItemTypical Range
Heritage architect (design + construction documents)$12,000–$30,000
Heritage Impact Statement$5,000–$15,000
Structural engineering$3,000–$8,000
DA fees (council)$8,000–$25,000 (based on construction cost)
Pre-application meeting + council correspondence$1,000–$4,000
Total pre-construction / approval cost$29,000–$82,000
Construction (second storey addition, 30–60m²)$160,000–$380,000
Total project budget range$190,000–$460,000

These figures reflect the additional costs relative to a non-heritage second storey addition. The approval process alone adds $15,000–$40,000 in professional fees and $8,000–$25,000 in council fees compared to a standard DA or CDC pathway. However, a well-executed heritage second storey addition that respects the original fabric can add significant value to a heritage home — Sydney heritage properties at the premium end of the market often command 15–25% premiums over comparable non-heritage properties.

What Heritage-Sensitive Designs Typically Look Like

The most commonly approved approach for adding a second storey to a heritage home in Sydney involves a clearly recessed upper floor — visible from the side and rear but not the street — with a lightweight material (usually Colorbond steel, zinc, or copper cladding) that reads as a modern addition rather than an attempt to replicate the original. Floor-to-ceiling glazing at the rear of the addition is common, providing natural light and emphasising the contemporary character of the new work. Roof pitch and form are typically simplified to distinguish from the original roof below.

Frequently Asked Questions

Is my house heritage listed?

Check the NSW State Heritage Register at heritage.dpie.nsw.gov.au (search by address or property description). Also check your council’s Local Environmental Plan via the NSW Planning Portal — search your address and look for a heritage overlay. Your council’s heritage officer can also confirm whether your property is listed and what the listing covers. Pearson Industries provides complimentary heritage status checks as part of our initial project consultation.

Do I need a heritage architect, or can a regular architect design a heritage addition?

Any registered architect can legally prepare drawings for a heritage DA. However, heritage planning officers and the Heritage Council of NSW pay close attention to the credentials and experience of the design team. Using an architect with demonstrable heritage experience significantly increases the likelihood of approval — and often reduces the number of revision cycles required during assessment. Pearson Industries works with a network of heritage architects across Sydney and can recommend practitioners based on your council and project type.

Can I use the CDC pathway for works to a heritage home?

No. Heritage-listed properties — both State Heritage Register items and locally listed items on council LEPs — are specifically excluded from the Complying Development Certificate (CDC) pathway under the Codes SEPP. All building works requiring approval on a heritage-listed property must go through the Development Application process with council (and, for SHR items, the Heritage Council of NSW). This applies to second storey additions, extensions, and most external alterations.

How long does heritage DA approval take in Sydney?

A heritage DA for a residential second storey addition typically takes 4–9 months from lodgement to consent. Allow an additional 3–5 months for pre-application engagement, design, and Heritage Impact Statement preparation before lodging. Total project timeline from first consultation to construction commencement is typically 9–18 months. Pearson Industries manages the entire approval process for heritage projects, coordinating architects, heritage consultants, and council engagement to keep the timeline as efficient as possible.